Let your light so shine!Installation of new lights
in Luther Memorial's nave: a photo progress report
| ||
Work began August 30 on replacement of the lamp fixtures in the nave. From September 5 through October 3, worship services were held in the Great Room, and the Adult Forum met in the Multipurpose Room of the Lutheran Campus Center next door. The project, includes eight new 36-inch-high, 16-inch-wide lanterns centered on the stained glass windows above the pews; lighting on the side aisles, and additional lighting at side walls of the choir balcony. Fixtures at the north walls of the east and west transepts will be replaced and lowered. Kubala Washatko Architects, LMH Lighting, Vogel Brothers, Custom Metal, and Forward Electric presented the plans. |
||
Before: August 29, 2004 |
||
![]() |
The Occupational Safety and Health Agency (OSHA) has said the church can no longer use the catwalk above the nave to replace bulbs in the six old "gym lights," some of which have burned out. The project will cost $225,000. Most of the money has been raised, but donations are still being sought. |
|
| The church is selling T shirts and polo shirts with the "Let Your Light So Shine" words, picture of a new light fixture, and the church name embroidered on the chest. Polo shirts, $23, and T shirts, $12, are available before and after Sunday services or at the church office. | ![]() |
|
| Home | Art | Groups | History | Location | Music | News | Pastors' Page |
Pictures |
Sunday, September 5, 2004 |
![]() |
| After services in the Great Room, parishoners take a peek at the progress made in the first week of work. |
![]() |
It's hard to see beyond the glare of the "gym lights," but almost all of the catwalk that blocked the view of the ceiling peak is gone. The pews have been moved aside to make room to work, and pieces of the catwalk are piled on the plywood-covered floor. | |
![]() |
![]() |
Both the large Austin organ (left) and the Steere organ in the east transept (right) are covered with plastic to protect them from construction dust. | ![]() |
| Home | Art | Groups | History | Location | Music | News | Pastors' Page |
Pictures |
Tuesday, September 21, 2004 |
||
The lift is extended to carry a worker up to connect one of the light fixtures.
One of the new fixtures is lighted. |
![]() |
|